The company has its own 150 km standard-gauge railroad, connecting the mine to its coal-loading terminal at Puerto Bolívar on the Caribbean coast. There are two 120-car unit trains, each carrying 12,000 tons of coal per trip. The round-trip time for each train, including loading and unloading, is about 12 hours. The coal facilities at the port are capable of loading 4,800 tons per hour on to vessels of up to 175,000 tons of dead weight. The mine, railroad and port operate 24 hours per day. Cerrejón directly employs 4,600 workers, with a further 3,800 employed by contractors. The reserves at Cerrejón are low-sulfur, low-ash, bituminous coal. The coal is mostly used for electric power generation, with some also used in steel manufacture. The surface mineable reserves for the current contract are 330 million tons. However, total proven reserves to a depth of 300 metres are 3,000 million